InduTimes

Home >  Product News > New Products & Technology

New Products & Technology

World's First 700 MW Ultra-Supercritical CFB Boiler Enters Operation in Yunnan

2026-11-11 16:44:26New Products & Technology54
The world's first 700 MW ultra-supercritical CFB boiler has entered operation in Yunnan, China, demonstrating advances in low-grade fuel combustion and emission control.

Introduction

On April 17, 2025, Yunnan Energy Investment Group's Honghe Power Plant in Yunnan Province, China, completed a 168-hour trial run of its 700 MW ultra-supercritical circulating fluidized bed (CFB) unit. The boiler, developed by Dongfang Boiler Group, is described by its manufacturer as the world's first 700 MW ultra-supercritical CFB boiler to enter commercial operation. The milestone matters beyond a single project: it marks a step change in how high-ash, high-moisture, low-grade fuels can be used for efficient power generation. For engineers and procurement teams evaluating CFB technology, the project offers useful lessons on combustion uniformity, water-wall safety, and emission control in large-scale units.

Project Overview and Operating Conditions

The Honghe project is located in Yunnan, a region characterized by high altitude and abundant low-grade lignite with high moisture and ash content. These conditions pose well-known challenges for boiler design: unstable ignition, low flame stability, and high flue-gas volume. The 700 MW unit is designed to burn such fuels while achieving ultra-supercritical steam parameters (main steam at 25–26 MPa, 600°C class, with reheat). According to the source, the unit passed its 168-hour trial on April 17, 2025, following first ignition on February 20, first synchronization on March 21, and full-load operation on April 5. During the trial, steam parameters reached design values, all heating surfaces operated without overtemperature, and emissions of dust, SO2, and NOx met ultra-low emission limits.

The Honghe plant now has a total capacity of 1,300 MW from one large and two smaller units, with an expected annual generation of more than 8 TWh. It is positioned as a key stability anchor for the southern Yunnan power grid.

Technical Challenges of Large-Scale CFB Boilers

Scaling CFB boilers to 700 MW and ultra-supercritical conditions introduces several engineering hurdles. The furnace cross-section becomes very large, making it difficult to achieve uniform fuel distribution, air penetration, and solids mixing. If combustion is uneven, localized hot spots can cause slagging, while oxygen-deficient zones increase CO and unburned carbon. Water-wall safety is another concern: at ultra-supercritical pressure, the fluid undergoes significant property changes, and flow instability or heat imbalance can lead to tube overheating. Furthermore, the large thermal inertia of a CFB furnace complicates load-following and temperature control during rapid ramping.

Design Solutions Applied in the Honghe Unit

The source states that Dongfang Boiler's team adopted several innovative measures to address these challenges. The boiler features a single furnace with four cyclones in an M-type layout, without an external heat exchanger (also called a J-valve or external bed). This compact arrangement aims to reduce footprint and improve solids circulation uniformity. Other reported features include:

  • Large-scale furnace uniformity control technology
  • Patented fully water-cooled partition walls
  • Patented multi-angle furnace structure
  • Ultra-low mass flux hydrodynamic technology
  • Fully steam-cooled cyclone separators and inlet/outlet duct design
  • Advanced thermodynamic system and thermal deviation control

These measures target even combustion, stable water/steam flow, and minimized thermal imbalance. The use of steam cooling for cyclones is notable because it avoids the need for high-temperature resistant castable linings and reduces maintenance.

Environmental Performance and Flue-Gas Treatment

The project includes a flue-gas desulfurization (FGD) and selective catalytic reduction (SCR) system, both supplied by Dongfang Boiler with proprietary technology. The FGD system is described as the world's first single-tower, single-loop design to achieve a desulfurization efficiency above 99.5%. This is achieved through a pH cascade control and differentiated spray layers. For high-sulfur coals, this offers a more economical route to ultra-low emissions compared with conventional multi-tower systems. The SCR system reduces NOx, and the combination ensures compliance with China's ultra-low emission standards (dust ≤10 mg/m³, SO2 ≤35 mg/m³, NOx ≤50 mg/m³ at 6% O2).

Implications for Global CFB Applications

The Honghe project demonstrates that ultra-supercritical CFB technology can be scaled to 700 MW while burning difficult fuels. For regions with abundant low-grade coal, this offers a pathway to higher efficiency and lower emissions compared with subcritical units. However, it is important to note that the design is tailored to Yunnan's specific fuel and altitude conditions. Direct transfer to other sites would require careful fuel analysis and engineering adaptation. The absence of an external heat exchanger may simplify the layout but could affect load control flexibility; the reported successful trial suggests that the design has been validated under the tested conditions, but long-term operational data will be needed to confirm reliability and availability.

Key Takeaways for Engineers and Procurement Teams

When evaluating large CFB boilers for low-grade fuels, several factors deserve attention:

  • Fuel flexibility: Verify the boiler's ability to handle the full range of expected fuel properties, including moisture, ash, and heating value variations.
  • Combustion uniformity: Ask for computational fluid dynamics (CFD) analysis and cold-flow test data to assess air and solids distribution.
  • Water-wall safety: Review hydrodynamic design, particularly for ultra-supercritical units, and ensure adequate margin against flow instability.
  • Emission control: Confirm that the FGD and SCR designs are matched to the fuel's sulfur and nitrogen content, and request performance guarantees.
  • Operational flexibility: Inquire about minimum stable load, ramp rate, and start-up time, especially if the unit will support variable renewable generation.

The Honghe project provides a reference point for these discussions, but each project must be engineered for its specific conditions.

Sources and References

Frequently Asked Questions

What is an ultra-supercritical CFB boiler?

An ultra-supercritical CFB boiler operates at steam pressures and temperatures above the critical point (typically ≥25 MPa, ≥600°C), achieving higher thermal efficiency than subcritical units. The circulating fluidized bed enables fuel flexibility and in-furnace emission control.

Why is the 700 MW milestone significant?

Scaling CFB boilers to 700 MW with ultra-supercritical parameters requires solving challenging issues in combustion uniformity, hydrodynamic stability, and emissions control. The Honghe project demonstrates that these challenges can be addressed in a commercial unit, opening the door to larger, more efficient CFB plants.

Can this technology be used outside China?

The design principles are applicable globally, but the specific configuration must be adapted to local fuel properties, altitude, and environmental regulations. Interested buyers should conduct a thorough feasibility study and require performance guarantees from the supplier.

What emissions performance was achieved?

During the trial, the unit met China's ultra-low emission standards for dust, SO2, and NOx. The FGD system is reported to achieve 99.5% desulfurization efficiency in a single tower, which is particularly relevant for high-sulfur fuels.